AXIS GLOBAL ENERGY - OFFSHORE REPORT - FEBRUARY 2026

Key Findings Summary

1

Since 2021, more than half (57%) of claims by count were found to be related to wind turbines (exclusive of foundation and transition piece), accounting for the greatest proportion of total incurred losses at 37%.

2

In terms of claims by count, inter array cables were a distant second at 14%. They also accounted for 14% of total claim amount.

3

Export cables make up only 6% of claims by count but represent the largest average claim at $18.8M, largely due to loss of revenue.

Wind turbine foundation claims follow with an average claim of $7.4M, reflecting the high costs associated particularly with pile running and pile rejection events.

4

More than two thirds of wind turbine claims by count relate to damage occurring to the drive train, with one third relating to the generator.

5

Operational phase claims increased in frequency over the period analyzed, while construction phase claims were largely steady throughout with an average claim of $6.4m—or $2.1m greater than the average operational claim.

The vast majority (>96%) of AXIS Global Energy claims featured in this analysis are CAR (Construction All Risks) and OAR (Operations All Risks), both of which require a physical damage trigger before physical damage costs and business interruption (loss of revenue) cover is provided. Additional claims include offshore and third party liability claims, as well as marine cargo.

  • Wind Turbine – Inclusive of tower, rotor nacelle assembly and electrical systems up until the wind turbine switchgear
  • Wind Turbine Foundation – Inclusive of piles, foundation structure, transition piece, landing platform and davit crane
  • Export Cable (Offshore) – Inclusive of HVAC and HVDC subsea export cables between the offshore substation and transition joint bay, also features export cable conduits (intertidal pipes) and CPS
  • Export Cable (Onshore) – Inclusive of HVAC and HVDC onshore export cables between the transition joint bay and onshore substation
  • Inter Array Cable – Inclusive of MVAC subsea export cables between the wind turbine and offshore substation
  • Onshore Substation – Inclusive of onshore electrical balance of plant, O&M building and foundations
  • Offshore Substation – Inclusive of topside, electrical balance of (to the cable drop) and foundations
  • Other – Includes TPL and CBI claims (TSO outages), in addition to lost or damaged contractor equipment, vessel damage and civil engineering works not directly related to the other project areas listed

Cookies | Terms | Privacy